APPLICATION OF CONSTRUCTION SCHEDULE FOR MONITORING AND CONTROL OF CIVIL ENGENEERING PROJECTS

 

Stanojlović Danijela1
 
1IMS Institut, Bulevar vojvode Misica 43 , Belgrade, Ova adresa el. pošte zaštićena je od spam napada, treba omogućiti JavaSkript da biste je videli
 

ABSTRACT  Full text (pdf)

Construction schedule becomes part of positive practice of our construction. The construction of Building and Residential Complex Stepa Stepanovic has been used for conducting research among responsible contractors on certain aspects of schedule execution, problems during its executions and use in construction process. The results of the research  show that there is lack of time and professional teams to produce detail construction schedule. Possiblities provided by the project management softwares are hugh and  should be used in order to better assses the current state of construction  and risks that accompany it.
 
Key words: construction schedule, project planning software
 

REFERENCES

[1]

Stanojlovic, D. (2009). Projekat organizacije i tehnologije građenja Stambeno-poslovni objekat SPO 6-4, Belville, Beograddiplomski rad. Beograd.

[2]

Stanojlovic, D. (2012). Projekat organizacije i tehnologije građenja za Objekat 2A Stambenoposlovnog kompleksa “Stepa Stepanovic”, Voždovacstručni rad. Beograd

[3]

Robinson, D. Michaela. (2011). A Contractor’s Guide to the FIDIC Conditions of Contract

[4]

Law on planning and construction, "Official Gazette of RS", no. 72/2009, 81/2009 - corr., 64/2010 – Decision of the Constitutional Court, 24/2011, 121/2012, 42/2013 - Decision of the Constitutional Court, 50/2013 - Decision of the Constitutional Court and 98/2013 – Decision of the Constitutional Court).

[5]

Draft Law on planning, design and construction, the Ministry of Civil Engineering and Urban Planning, Republic of Serbia, Belgrade. (2013).

[6]

Specific common practices of civil engineering, "Official Gazette of SFRY", No.18 / 77. 

[7]

Rulebook on the manner and procedure of technical supervision during construction of objects, "Official Gazette of RS", No. 7/2010 of 02/19/2010.

[8]

Mitrovic, Z., Obradovic, V., Mihic, M. (2011). Uporedna analiza softvera za upravljanje projektima, Operacioni menadžment u funkciji održivog ekonomskog rasta i razvoja Srbije 2011-2020. Beograd. VIII skup   privrednika i naučnika.

[9]

General dynamic plan for the construction of objects of residential - commercial complex Stepa Stepanovic (Objects 6K, 6L, 7A, 7B, 2A and 5A) (2012-2013). Belgrade.

[10]

Interview: Practical experience of the responsible contractor in the development and implementation of dynamic plans for the construction of residential and commercial complex Stepa Stepanovic, Belgrade, 2012-2013. Belgrade. (2014). 

 

 

 

 

  

  

  

  

  

  

 

   

 
Copyright Tehnički institut Bijeljina, 2010.
Web dizajn : Stanko Zarić

uređuje: www.asteh.com